Balance of Plant (BOP) Group 3

Category: Electronic engineering, electronics, mechanical engineering, material engineering, IT


Deadline: 23/10/2020 r.

 

Announcement:

Balance of Plant (BOP) Group 3

The purpose of this contract is primarily related to the installation of systems in the main Control Room in Building 71, and other ITER site buildings; the ITER systems included in the scope of work of BOP 3 contract are the following:

PBS26 – Cooling Water System
PBS45 – CODAC
PBS46 – Central Interlock System
PBS48 – Central Safety System
PBS69 – Access Control & Security Systems

The scope covered by the BOP Group 3 Contract is located in Buildings 32, 33, 34, 35, 36, 37, 38, 39, 41, 44, 45, 46, 47, 52, 61, 64, 67, 68, 69, 71, 74, 75 and Area 30, all these buildings are in Worksite areas 3, 4 and 5; all the listed buildings are mainly for interconnection cables between buildings and for the installation of access control and security systems.

 

CFN Deadline Date :
23 / 10 / 2020

 

Technical summary

Information on ITER website